User Tools

Site Tools


installation_fp_sci

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
Next revision Both sides next revision
installation_fp_sci [2017/03/06 12:31]
pereira [Installing FP scintillator]
installation_fp_sci [2017/06/13 12:19]
pereira
Line 1: Line 1:
 ====== Installation of focal-plane scintillator ====== ====== Installation of focal-plane scintillator ======
  
-==== Vent focal-plane chamber ====+===== Vent focal-plane chamber =====
   * Open the [[hv_bias|HV Remote Control]] GUI and ensure that the focal-plane detectors are unbiased   * Open the [[hv_bias|HV Remote Control]] GUI and ensure that the focal-plane detectors are unbiased
   * Open the [[gas_handling_system#labview_control_program|Labview gas handling system]] and verify that there is no gas in the CRDCs and IC. Open valves **4** (IC supply), **5** (IC bypass), **6** (IC focal-plane bypass), **20** (CRDC supply), **21** (CRDC bypass), and **22** (CRDC focal-plane bypass). The rest of the valves should be closed   * Open the [[gas_handling_system#labview_control_program|Labview gas handling system]] and verify that there is no gas in the CRDCs and IC. Open valves **4** (IC supply), **5** (IC bypass), **6** (IC focal-plane bypass), **20** (CRDC supply), **21** (CRDC bypass), and **22** (CRDC focal-plane bypass). The rest of the valves should be closed
Line 11: Line 11:
   * Wait until the chamber is vented (few hours). The **I261PG** Pirani Gauge should read slightly above atmospheric pressure (due to the dry N2 flow pumped to the chamber). The window **VENT STATUS** in PanelMate should display "VENT VALVE OPEN". The window **PUMPDOWN STATUS** should display "PUMPDOWN STOPPED"   * Wait until the chamber is vented (few hours). The **I261PG** Pirani Gauge should read slightly above atmospheric pressure (due to the dry N2 flow pumped to the chamber). The window **VENT STATUS** in PanelMate should display "VENT VALVE OPEN". The window **PUMPDOWN STATUS** should display "PUMPDOWN STOPPED"
  
-==== Open focal-plane chamber ====+===== Open focal-plane chamber =====
  
-  * After venting the FP chamber, the pressure inside the chamber is slightly above atmospheric due to the dry N2 pumped. Before opening the chamber, it is recommended to vent the extra N2 by "forcing" the chamber flange with e.g. a screwdriver {{:wiki:screwdriver-flange.jpg?350}}+  * After venting the FP chamber, the pressure inside the chamber is slightly above atmospheric due to the dry N2 pumped. Before opening the chamber, it is recommended to vent the extra N2 by "forcing" the pressure-relief valve  with e.g. a screwdriver {{:wiki:screwdriver-flange.jpg?350}}
   * Unlock the padlock protecting the power brakers of the switch controls to open the chamber, and press the **START** button {{:wiki:padlock-note.jpg?350|Padlock}}   * Unlock the padlock protecting the power brakers of the switch controls to open the chamber, and press the **START** button {{:wiki:padlock-note.jpg?350|Padlock}}
   * Turn the switch to open the clamps holding the FP chamber. The weight held by the hydraulic piston will increase {{:wiki:switch-clamps.jpg?250|Switch clamps}} {{:wiki:clamps.jpg?400|Clamps holding FP chamber}} {{:wiki:scale.jpg?350|Scale FP chamber}}   * Turn the switch to open the clamps holding the FP chamber. The weight held by the hydraulic piston will increase {{:wiki:switch-clamps.jpg?250|Switch clamps}} {{:wiki:clamps.jpg?400|Clamps holding FP chamber}} {{:wiki:scale.jpg?350|Scale FP chamber}}
Line 19: Line 19:
  
  
-==== Installing FP scintillator ====+===== Installing FP scintillator =====
  
   * The figure below shows the FP chamber open, with the "old" FP scintillator to be replaced by the new one {{:wiki:E1-view.jpg?350|FP chamber opened}}   * The figure below shows the FP chamber open, with the "old" FP scintillator to be replaced by the new one {{:wiki:E1-view.jpg?350|FP chamber opened}}
Line 33: Line 33:
  
  
-==== Closing focal-plane chamber ==== +===== Closing focal-plane chamber ===== 
-  Turn the switch to move the chamber to position "UP", and keep it that way for about 10 minutes (the time it takes the chamber to be closed) +  Turn the switch to move the chamber to position "UP", and keep it that way for about 10 minutes (the time it takes the chamber to be closed) 
-  When the chamber is almost close, turn the know to close the clamps +  When the chamber is almost close, turn the know to close the clamps 
-  Before pumping the chamber down, make sure that the scintillator is properly connected. This can be done by biasing the detector and checking the signals, either from the scalers or with a scope. One should clearly see cosmic rays; if that is not the case, the phototubes are likely miss connected +  Before pumping the chamber down, make sure that the scintillator is properly connected. This can be done by biasing the detector and checking the signals, either from the scalers or with a scope. One should clearly see cosmic rays; if that is not the case, the phototubes are likely miss connected 
-  - In order to pumpdown the chamber, make sure that the manual vent valve is closed. Start manual pump to get a pressure below 50 mtorr {{:wiki:ManualValve-fp.jpg?350|Manual valve pump}} + 
-  Close the manual pump; open PanelMate **S800vac** and go to page 07. Select window **PUMPDOWN STATUS** and click on button **START PUMPDOWN**. The **PUMPDOWN STATUS** and **VENT STATUS** windows should display "PUMPDOWN IN PROGRESS" +===== Pumping focal-plane chamber ===== 
-  Wait for some hours until vacuum is good+  * Make sure that the pressure-relief valve (see above) is in place (closed). 
 +  * In order to pumpdown the chamber, make sure that the manual vent valve is closed. Start manual pump to get a pressure below 50 mtorr {{:wiki:ManualValve-fp.jpg?350|Manual valve pump}} 
 +  Close the manual pump; open PanelMate **S800vac** and go to page 07. Select window **PUMPDOWN STATUS** and click on button **START PUMPDOWN**. The **PUMPDOWN STATUS** and **VENT STATUS** windows should display "PUMPDOWN IN PROGRESS" 
 +  Wait for some hours until vacuum is good