installation_fp_sci [2023/02/17 20:16]
pereira [Pumpdown of FP Chamber]
installation_fp_sci [2023/02/17 20:45]
pereira [Pumpdown of FP Chamber]
Line 43: Line 43:
   - If the TMP is off and Foreline Valve (FV) is closed, open the Roughing Valve (RV) briefly (2 seconds) by clicking **Open** and observe the behavior of the pressure gauges. If they all decrease at the same rate, again click **Open** to begin rouging out the chambers.   - If the TMP is off and Foreline Valve (FV) is closed, open the Roughing Valve (RV) briefly (2 seconds) by clicking **Open** and observe the behavior of the pressure gauges. If they all decrease at the same rate, again click **Open** to begin rouging out the chambers.
   - If the TMP is still on (this could be the case for a short vent period), turn it off and close the foreline valve (FV) before doing step 6.   - If the TMP is still on (this could be the case for a short vent period), turn it off and close the foreline valve (FV) before doing step 6.
-  - When the BPG reads below 200 mTorr, **Close** RV and **Open** FV. Turn the TMP on if it is not already. When the TMP is “at speed” **Open** the TGV.  +  - When the BPG reads below 200 mTorr, **Close** RV and **Open** FV. Turn the TMP on if it is not already. When the TMP is “at speed” (~30,000 RPM), **Open** the TGV.  
-  - NOTE: before reach "at speed", pressure in the chamber, as read by BPG, might increase to a point where TGV can not be open. If that is the case, turn off the turbo pump, close FV, and repeat the sequence from step until pressure goes below 100 mTorr. Then continue +  - NOTE: before reach "at speed", pressure in the chamber, as read by BPG, might increase to a point where TGV can not be open. If that is the case, turn off the turbo pump, close FV, and repeat steps 6, 7, 8 but this time, wait for BPG to read below 100 mTorr. Then try again step 8.
-  - If the TMP was off before opening the TGV, the chamber pressure may have risen to a point where the TGV closes automatically. If the BPG still reads < 1 Torr, attempt to **Open** the TGV again.+
   - Allow the TMP to pump on the system until the IG reads < 1E-5 Torr.   - Allow the TMP to pump on the system until the IG reads < 1E-5 Torr.
   - On the “FP_State_Buttons” page click **RUN** to enter run mode.   - On the “FP_State_Buttons” page click **RUN** to enter run mode.