- | ===== Vent focal-plane chamber ===== | + | ===== Vent Intermediate-image chamber ===== |
Requirements: | Requirements: | ||
Line 27: | Line 27: | ||
* Open **S800Vac** and go to page 03 (" | * Open **S800Vac** and go to page 03 (" | ||
* Check box " | * Check box " | ||
- | {{: | + | {{: |
* In order to begin venting process, select that box and click "BEGIN VENTING PROCEDURE" | * In order to begin venting process, select that box and click "BEGIN VENTING PROCEDURE" | ||
* Box "VENT STATUS" | * Box "VENT STATUS" | ||
- | * Turbo gate valve **I214GV** will be automatically closed and pressure in chamber will start rising (as seen in **I215PG**) {{: | + | * Turbo gate valve **I214GV** will be automatically closed and pressure in chamber will start rising (as seen in **I215PG**) {{: |
- | * When **I215PG** reads atmospheric pressure, select the box "VENT STATUS" | + | * When **I215PG** reads atmospheric pressure, select the box "VENT STATUS" |
* The status in the box "VENT STATUS" | * The status in the box "VENT STATUS" | ||
* You can now open the chamber | * You can now open the chamber | ||
+ | |||
+ | |||
+ | ===== Pumping Intermediate-image chamber ===== | ||
+ | Requirements: | ||
+ | * Verify that Chamber is closed and pressure-relief valve (north side of the chamber) is properly closed (NOTE: sometimes, due to overpressure from dry N2 during the venting procedure, the O-ring in pressure-relief valve flange is moved out of place) | ||
+ | * Verify that PPACs are not biased by opening the [[HV bias|HV GUI]] | ||
+ | * IMPORTANT: Close manual roughing pump valve close to the Intermediate-image chamber (see picture) | ||
+ | * Insert PPACs/turn on light (Diagnostic Drives PanelMate) and verify condition through sight window on south side of the chamber (be careful no to bump the bullet camera). | ||
+ | * Open **S800Vac** and go to page 03 (" | ||
+ | * Check " | ||
+ | * Slowly crack manual roughing valve | ||
+ | * Start slow (< 1 Torr/sec). Pressure is displayed in the digital display of the Granville-Phillips 275 Mini-Convectron gauge, sitting on top of the chamber (or in **I215PG** in **S800Vac** PanelMate) | ||
+ | * Verify PPACs changing shape through sighting window | ||
+ | * When PPACs equalize, increase to 5 Torr/sec | ||
+ | * Once roughing valve is fully open, retract PPACs and turn lights off. | ||
+ | * When the pressure in **I215PG** is below 200 mTorr, the Turbo Pump will start automatically through the following sequence: | ||
+ | * **I214RV** will be closed | ||
+ | * **I214FV** will be opened | ||
+ | * **I214GV** will be opened | ||
+ | * When the pressure ready by **I215PG** is few mTorr, you can turn on the ion gauge **I213IG**. Good vacuum will take ~1-2 hours. | ||