pereira [Filling Intermediate-image delay PPAC]
venting_pumping_intermediate_image_box [2018/12/19 11:48]
pereira [Filling Intermediate-image delay PPAC with gas]
Line 3: Line 3:
   * [[#Vent Intermediate-image chamber|Venting Intermediate-image chamber]]   * [[#Vent Intermediate-image chamber|Venting Intermediate-image chamber]]
   * [[#Pumping Intermediate-image chamber]]   * [[#Pumping Intermediate-image chamber]]
-  * [[#Filling Intermediate-image delay PPAC]]+  * [[#Filling/Removing gas in Intermediate-image delay PPAC]]
  
 ===== General information ===== ===== General information =====
Line 78: Line 78:
  
 Requirements: PanelMate files **S3_Gas_Handling** and **S800Vac** Requirements: PanelMate files **S3_Gas_Handling** and **S800Vac**
 +
 +==== Filling Intermediate-image delay PPAC with gas ====
   * Verify that PPACs are not biased:   * Verify that PPACs are not biased:
         * Check that the detectors are unbiased by opening the [[HV bias|HV GUI]]         * Check that the detectors are unbiased by opening the [[HV bias|HV GUI]]
Line 97: Line 99:
         * The valves status will be: V1 (open), V2 (closed), V3 (closed), V4 (open), V5 (closed), V6 (closed, I214V_NCL (enabled)         * The valves status will be: V1 (open), V2 (closed), V3 (closed), V4 (open), V5 (closed), V6 (closed, I214V_NCL (enabled)
         * You can now turn on the detectors         * You can now turn on the detectors
 +
 +
 +
 +
 +==== Removing gas from Intermediate-image delay PPAC ====
 +  * Verify that PPACs are not biased:
 +        * Check that the detectors are unbiased by opening the [[HV bias|HV GUI]]
 +        * Notify the system of the bias-off state by selecting the "I214BON_CONFIRM" box in **S3_Gas_Handling** and clicking "PP BIAS OFF CONFIRMED"
 +  * Verify that PPACs are in automatic mode with gas flowing (**S3_Gas_Handling**)
 +        * The "GH System Status box should read "Auto Gas Flow Estab"
 +        * If gas is flowing but the system is not in the automatic mode, consult the Beam Physicists or Device Physicist. This typically requires to verify that the system is in a controlled status. In particular, the "I214BON_CONFIRM" box should indicate "PP BIAS OFF CONFIRMED", and the valves should indicate:
 +              * I214 Gas Sup V1 (open)
 +              * Gas Lin Pmp out V2 (closed)
 +              * Flow Bypass V3 (closed)
 +              * Det Return V4 (open)
 +              * Det Bypass V5 (closed)
 +              * Chmbr Bypass (closed)
 +              * I1214V_NCL (enabled) 
 +  * PanelMate box "Gas Removal Control" should indicate "OK to Start Gas Removal". Select that box and click on "Start Gas Removal"
 +        * Valve V2 (Gas lin pmp out) will be opened and I214V_NCL will change from closed to "ENABLED"