emergency_shutdown [2020/03/22 20:13]
pereira [Communication before and after completion of Shutdown]
emergency_shutdown [2020/11/06 13:17]
pereira
Line 1: Line 1:
-====== Emergency Shutdown ======+====== Shutdown S800/S3 Vault ======
 The following checklist describes the steps to follow during an emergency shutdown. The assumed scenario is that where the entire S800 (and S3 vault) must be turned off due to multiple reasons. Please, be aware that the procedures described below involve many different systems in the lab. As such, it is highly recommended to coordinate with operations staff using all available communication channels (face-to-face, hourlog, 8am-meeting and short-meeting). Also, as long as it is possible (the nature of an emergency shutdown may require to act very quickly), a Work-Control-Plan should be submitted.  The following checklist describes the steps to follow during an emergency shutdown. The assumed scenario is that where the entire S800 (and S3 vault) must be turned off due to multiple reasons. Please, be aware that the procedures described below involve many different systems in the lab. As such, it is highly recommended to coordinate with operations staff using all available communication channels (face-to-face, hourlog, 8am-meeting and short-meeting). Also, as long as it is possible (the nature of an emergency shutdown may require to act very quickly), a Work-Control-Plan should be submitted. 
  
Line 7: Line 7:
  
 ===== Communication before and after completion of Shutdown ===== ===== Communication before and after completion of Shutdown =====
-  * Give heads up to any experimenters planning to run in the vault +  * Give heads up to Operations (beam coordinator) 
-  * Heads up to Operations (beam coordinator)+  * Heads up to any experimenters planning to run in the vault
   * Heads up to GRETINA group   * Heads up to GRETINA group
   * Heads up to Cryogenics group   * Heads up to Cryogenics group
Line 31: Line 31:
 ===== Vacuum =====  ===== Vacuum ===== 
   * Close ALL gate valves   * Close ALL gate valves
-  * VERY IMPORTANT: Vent FP box, but leave dry N2 flowing (it requires "forcing open" pressure-relieve valve)+  * VERY IMPORTANT: Vent FP box, but leave dry N2 flowing (it requires opening the lift-off disk of the pressure-relief valve)
   * Make sure that FP Turbo-pump is OFF. Turn OFF Turbo Pump chiller   * Make sure that FP Turbo-pump is OFF. Turn OFF Turbo Pump chiller
   * Turn off CRDCs chiller   * Turn off CRDCs chiller
Line 50: Line 50:
   * Turn off all crates in S800 rack (S3 vault)   * Turn off all crates in S800 rack (S3 vault)
   * Turn off all crates in dU6   * Turn off all crates in dU6
-  * Shut down s800fp PC (in S3) +  * Reboot s800fp PC (in S3) 
-  * Shut down u6pc5 +  * Reboot down u6pc5 
-  * Shut down spdaq50+  * Reboot down spdaq50
  
  
Line 59: Line 59:
   * Turn on FAN   * Turn on FAN
   * If possible, reduce He lead flows (not essential)    * If possible, reduce He lead flows (not essential) 
-  * Shut down S3 vault PC (in mezzanine level of S3) 
   * Leave all lights in the vault ON   * Leave all lights in the vault ON
   * Leave vault unsecured and fully accessible   * Leave vault unsecured and fully accessible