Both sides previous revision Previous revision | Next revision Both sides next revision | ||
installation_fp_sci [2019/07/01 09:05] pereira [Vent focal-plane chamber] |
installation_fp_sci [2019/07/01 09:08] pereira [Vent focal-plane chamber] |
||
---|---|---|---|
Line 16: | Line 16: | ||
{{: | {{: | ||
* Wait until the chamber is vented (few hours). The **I261PG** Pirani Gauge should read slightly above atmospheric pressure (due to the dry N2 flow pumped to the chamber). The window **VENT STATUS** in PanelMate should display "VENT VALVE OPEN". The window **PUMPDOWN STATUS** should display " | * Wait until the chamber is vented (few hours). The **I261PG** Pirani Gauge should read slightly above atmospheric pressure (due to the dry N2 flow pumped to the chamber). The window **VENT STATUS** in PanelMate should display "VENT VALVE OPEN". The window **PUMPDOWN STATUS** should display " | ||
- | * Meanwhile, turn the turbo pump off using PanelMate | + | * Meanwhile, turn the turbo pump off using PanelMate **S800vac**: select box **Turbo pump focal plane detector I260TP** can clock " |
+ | * When the Turbo pump is fully stopped, switch off the chiller located near the S800 electronics rack | ||
* When the chamber is fully vented, select **VENT STATUS** and click **STOP VENTING PROCEDURE**. This will automatically close the vent valve **I260VV** | * When the chamber is fully vented, select **VENT STATUS** and click **STOP VENTING PROCEDURE**. This will automatically close the vent valve **I260VV** | ||
* Close the manual vent valve | * Close the manual vent valve |