vacuum_control [2016/11/09 15:29] pereira [Venting analysis-line lower-dipole section] |
vacuum_control [2016/11/09 15:29] pereira [Venting analysis-line lower-dipole section] |
||
---|---|---|---|
Line 56: | Line 56: | ||
- Go to page 4 (" | - Go to page 4 (" | ||
- Window "VENT STATUS" | - Window "VENT STATUS" | ||
- | - Click on "VENT STATUS" | + | - Click on "VENT STATUS" |
- Walk to the bottom level of the S3 vault, near the intermediate image box. Locate the I226PG Pirani gauge and ensure that it reads rough-vacuum pressure (few militorr). | - Walk to the bottom level of the S3 vault, near the intermediate image box. Locate the I226PG Pirani gauge and ensure that it reads rough-vacuum pressure (few militorr). | ||
- Slowly open the manual valve (see picture below) and verify that the pressure read in I226PG raises slowly. | - Slowly open the manual valve (see picture below) and verify that the pressure read in I226PG raises slowly. |