Line 1: Line 1:
-===== Venting/pumping Intermediate Image box and filling PPACs with gas ===== +====== Venting/pumping II chamber & emptying/filling gaseous detectors ====== 
-The procedures to vent/pump the S800 Intermediate Image box, and/or filling the PPAC detectors with gas must be done carefully to ensure that the PPACs are not damaged. For instance, before venting the chamber, we have to make sure that the PPACs are empty and equalized with respect to the vacuum in the chamber. In order to avoid errors, an automated gas handling system (II-GHS) was designed to perform these tasks safety. The system is schematically illustrated in the figure belowIt shows the status of the valves (red: closed, white: openwhen the intermediate image chamber is under vacuum and the PPACs are filled with gas:+  * [[#General information]] 
 +  * [[#Emptying Detectors]] 
 +  * [[#Venting the Chamber]] 
 +  * [[#Evacuating the Chamber]] 
 +  * [[#Filling and Running Detectors]] 
 +  * [[#Troubleshooting]] 
 +===== General information ===== 
 +The procedures to vent/pump the S800 Intermediate Image box, and/or filling the PPAC detectors with gas must be done carefully to ensure that the PPACs are not damaged. For instance, before venting the chamber, we have to make sure that the PPACs are empty and equalized with respect to the vacuum in the chamber. In order to avoid errors, an automated gas handling system (II-GHS) was designed to perform these tasks safely. The II-GHS equipment (valves, flow-meter, pipes, isobutane gas bottleetc.) are located on the west balcony of the top level in the S3 vault (see figure below):
  
-{{:wiki:ghsiippacs.png?1000|Gas Handling System of S800 Intermediate Image}} +{{:wiki:IIGHShardware.jpeg|Gas Handling System of S800 Intermediate Image}} 
  
-The II-GHS equipment (valves, flow-meter, pipes, etc.) are located on the west balcony of the top level in the S3 vault (see figure below):+The GHS is operated remotely through CS studioIts page can be found on the EXP network through FRIB EXP Main → S800 → GHS Pages (Secondary Pages) → Intermediate Image PPAC and is shown below
  
-{{:wiki:IIGHShardware.jpg?600|Gas Handling System of S800 Intermediate Image}}  +{{:wiki:ii-ppac-ghs-css.png|}}
-==== Vent focal-plane chamber ==== +
-Requirements: PanelMate files **S3_Gas_Handling** and **S800Vac**+
  
-  * Verify that PPACs are in automatic mode with gas removed (**S3_Gas_Handling**) +The layout of the II-GHS is shown below.
-        *  The "GH System Status box should read "Auto Mode Gas Removed" +
-        * If gas is removed but the system is not in the automatic mode, consult the Beam Physicists or Device Physicist. NOTE: the only valves that should be open in **S3_Gas_Handling** are the "Det Bypass" and "Chmbr Bypass  +
-  * Verify that PPACs are not biased: +
-        * Check that the detectors are unbiased by opening the [[HV bias|HV GUI]] +
-        * Notify the system of the bias-off state by selecting the "I214BON_CONFIRM" box in **S3_Gas_Handling** and clicking "PP BIAS OFF CONFIRMED" +
-  * Isolate chamber by closing gate valves **I212GV** and **I215GV** +
-  * [[Vacuum control|Turn off]] ion gauge **I213IG**  +
-  * Open **S800Vac** and go to page 03 ("Intermediate image box vacuum system sec 15") +
-  * Check box "PUMPDOWN STATUS INTERMEDIATE IMAGE BOX". It should read "Good vacuum"  +
-{{:wiki:iis800vac_pumped.jpg?350|S800vac Panel Mate}}.  +
-  * In order to begin venting process, select that box and click "BEGIN VENTING PROCEDURE" +
-        * Box "VENT STATUS" should change from "VENT PROCEDURE STOPPED" to "WAITING FOR VENT TIMER".  +
-        * Turbo gate valve **I214GV** will be automatically closed and pressure in chamber will start rising (as seen in **I215PG**) {{:wiki:iis800vac_startventing.jpg?350|S800vac Panel Mate: start venting}}.  +
-        * When pressure in **I215PG** reaches atmospheric pressure, stop the venting process by selecting the box "VENT STATUS" and clicking "STOP VENTING PROCESS" {{:wiki:iis800vac_stopventing.jpg?350|S800vac Panel Mate: stop venting}}+
  
-        * The status in the box "VENT STATUS" should change from "WAITING FOR VENT TIMER" to "VENT PROCEDURE STOPPED" +{{:wiki:ii-ppac-ghs-layout.png|}}
-        * You can now open the chamber+
  
 +The operational states of the II-GHS are shown in the diagram below.
 +
 +{{:wiki:ii-ppac-ghs-operationalstates.png|}}
 +
 +===== Emptying Detectors =====
 +  - Double check that the detectors have been unbiased.
 +  - Set “PPAC Setpoint” to 0 Torr.
 +  - Click **EMPTY** on the “GHS_II-PPAC_Main” page to open valves #3 and #4 which will allow for pumping out the gas quickly.
 +  - When “PPAC Pressure” reads < 0.1 Torr, turn off IG and click **MAN** and then **AUTO**. This will open valve #6 to release the remaining gas into the diagnostics box.
 +  - Monitor D2340 pumping station and ensure the TMP stays on and TGV remains open. If not, contact the Vacuum Operation group.
 +  - Valves #1-5 should be closed and valve #6 should remain open. From this state click **VENT** and then **PUMP** to enter pump mode and leave the system in this state until it is ready to be filled.
 +===== Venting the Chamber =====
 +
 +From the S800 Main Vacuum page, go to the Intermediate Image - RBT_BTS32 D2430 Pumping Station page, and ensure
 +  * that the PPACs have been unbiased,
 +  * that this pumping station has been isolated by having the gate valves **D2426 BGV** and **D2436 BGV** closed, and that the IG has been turned off, and
 +  * that the turbo pump gate valve **TVG** is closed.
 +
 +The TMP can be turned off at this time.
 +
 +To vent the chamber:
 +  - Let the Control Room and the Vacuum Operation Group be aware as EXP alarms may occur,
 +  - put the GHS in vent mode by clicking **VENT** (valves #5 and #6 are open),
 +  - monitor **RBT_BTS32:BPG_D2430:VP_RD** and **S800_GHS:PI_D2431:V_RD_AB** in a data browser,
 +  - ensure that **RV**, the valve to the roughing pump, is closed, and
 +  - open **Vent** valve to start venting.
 +
 +The PPAC pressure S800_GHS:PI_D2431:V_RD_AB should closely follow the chamber pressure  
 +RBT_BTS32:BPG_D2430:VP_RD up to about 10 Torr, which is the upper limit of the range of the gauge for S800_GHS:PI_D2431:V_RD_AB.
 +===== Evacuating the Chamber =====
 +
 +Ensure
 +  * that the chamber is closed
 +  * that the pressure-relief mechanism (on the north side of the chamber, see picture below) is sealing (if not, adjust the flange back in place)
 +{{ :wiki:iipressurereliefmechanism.jpeg?600 |}}
 +  * that the manual valve (see picture below) is closed.
 +{{ :wiki:iimanualvalve.jpeg |}}
 +
 +To evacuate the chamber:
 +  - double-check and make sure that the manual valve is closed,
 +  - put the GHS in pump mode by clicking **PUMP** (valves #3, #5, #6 are open),
 +  - close **FV** below the TMP, and
 +  - open **RV**.
 +  - A message window, which reads, "Roughing Valve should only be opened if Manual Valve is CLOSED. Confirm Manual Valve is CLOSED before proceeding." of the manual valve is confirmed to be closed, acknowledge the message and click "Yes". This will open **RV**.
 +  - now open the manual valve slowly while watching the local display of the Pirani gauge. Open slowly such that the pressure reading (in Torr) goes down by about 1 unit per second initially. The valve needs to open more as the pressure goes further down.
 +  - On the CSS window, after D2430 turns to yellow indicating that the section is in "POOR VACUUM", wait until the BPG reading to go below 100 mTorr before closing RV and opening FV.
 +  - Turn on TMP, and wait until it reaches the normal rotation (~40,000 rpm).
 +  - Open **TGV**.
 +  - Be sure to go back to S3 and close the manual valve.
 +===== Filling and Running Detectors =====
 +  - If in Vent Mode, click **PUMP** then click **RUN** to enter Run Mode. The valves #1 opens and #3 remains open (#5 and #6 will be closed, and the GHS lines will be isolated from the chamber).
 +  - If in Pump Mode, click **RUN** to enter Run Mode.
 +  - Plot and monitor IG_D2430:VP_RD while filling. Ion gauge reading will increase but should remain <1E-5 Torr when PPACs are running at full pressure. 
 +  - Step up “PPAC Setpoint” by 1 Torr from 0 to 6 Torr. Allow the “PPAC Pressure” to stabilize for 15 seconds at each step. This should be a quick process but **DO NOT** simply set the “PPAC Setpoint” to 6 Torr as the gas flow could overwhelm the system.
 +  - PPAC pressure should stabilize after ~1 min. HV may now be turned on to operate the PPACs.
 +
 +===== Troubleshooting =====
 +  - If any issues are encountered during filling, running, or emptying, contact the Vacuum Operation group for assistance.
venting_pumping_intermediate_image_box.1497293529.txt.gz · Last modified: 2017/06/12 14:52 by pereira