User Tools

Site Tools


venting_pumping_intermediate_image_box

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
venting_pumping_intermediate_image_box [2018/12/19 11:42]
pereira [Venting/pumping Intermediate Image box and filling PPACs with gas]
venting_pumping_intermediate_image_box [2024/01/12 09:37] (current)
noji [Filling and Running Detectors]
Line 1: Line 1:
-====== Venting/pumping Intermediate Image box and filling PPACs with gas ======+====== Venting/pumping II chamber & emptying/filling gaseous detectors ======
   * [[#General information]]   * [[#General information]]
-  * [[#Vent Intermediate-image chamber|Venting Intermediate-image chamber]] +  * [[#Emptying Detectors]] 
-  * [[#Pumping Intermediate-image chamber]] +  * [[#Venting the Chamber]] 
-  * [[#Filling/Removing gas in Intermediate-image delay PPAC]] +  * [[#Evacuating the Chamber]] 
 +  * [[#Filling and Running Detectors]] 
 +  * [[#Troubleshooting]]
 ===== General information ===== ===== General information =====
-The procedures to vent/pump the S800 Intermediate Image box, and/or filling the PPAC detectors with gas must be done carefully to ensure that the PPACs are not damaged. For instance, before venting the chamber, we have to make sure that the PPACs are empty and equalized with respect to the vacuum in the chamber. In order to avoid errors, an automated gas handling system (II-GHS) was designed to perform these tasks safely. The system is schematically illustrated in the figure below. It shows the status of the valves (red: closed, white: open) when the intermediate image chamber is under vacuum and the PPACs are filled with gas (NOTE: This figure was taken from the A1900 GHS included in Barney. A similar GUI for the S800 II PPACs is not yet available): +The procedures to vent/pump the S800 Intermediate Image box, and/or filling the PPAC detectors with gas must be done carefully to ensure that the PPACs are not damaged. For instance, before venting the chamber, we have to make sure that the PPACs are empty and equalized with respect to the vacuum in the chamber. In order to avoid errors, an automated gas handling system (II-GHS) was designed to perform these tasks safely. The II-GHS equipment (valves, flow-meter, pipes, isobutane gas bottle. etc.) are located on the west balcony of the top level in the S3 vault (see figure below):
- +
-{{:wiki:ghsiippacs.png?1000|Gas Handling System of S800 Intermediate Image}}  +
- +
-The II-GHS equipment (valves, flow-meter, pipes, isobutane gas bottle. etc.) are located on the west balcony of the top level in the S3 vault (see figure below): +
- +
-{{:wiki:IIGHShardware.jpg?600|Gas Handling System of S800 Intermediate Image}}  +
- +
- +
  
 +{{:wiki:IIGHShardware.jpeg|Gas Handling System of S800 Intermediate Image}} 
  
 +The GHS is operated remotely through CS studio. Its page can be found on the EXP network through FRIB EXP Main → S800 → GHS Pages (Secondary Pages) → Intermediate Image PPAC and is shown below. 
  
 +{{:wiki:ii-ppac-ghs-css.png|}}
  
-===== Vent Intermediate-image chamber ===== +The layout of the II-GHS is shown below.
-Requirements: PanelMate files **S3_Gas_Handling** and **S800Vac**+
  
-  * Verify that PPACs are in automatic mode with gas removed (**S3_Gas_Handling**) +{{:wiki:ii-ppac-ghs-layout.png|}}
-        *  The "GH System Status box should read "Auto Mode Gas Removed" +
-        * If gas is removed but the system is not in the automatic mode, consult the Beam Physicists or Device Physicist. NOTE: the only valves that should be open in **S3_Gas_Handling** are the "Det Bypass" and "Chmbr Bypass  +
-  * Verify that PPACs are not biased: +
-        * Check that the detectors are unbiased by opening the [[HV bias|HV GUI]] +
-        * Notify the system of the bias-off state by selecting the "I214BON_CONFIRM" box in **S3_Gas_Handling** and clicking "PP BIAS OFF CONFIRMED" +
-  * Open **S800Vac** and go to page 03 ("Intermediate image box vacuum system sec 15") +
-  * Isolate chamber by closing gate valves **I212GV** and **I215GV** +
-  * [[Vacuum control|Turn off]] ion gauge **I213IG**  +
-  * Check box "PUMPDOWN STATUS INTERMEDIATE IMAGE BOX". It should read "Good vacuum"  +
-{{:wiki:iis800vac_pumped.jpg?500|S800vac Panel Mate}}.  +
-  * In order to begin venting process, select box "VENT STATUS" and click "BEGIN VENTING PROCEDURE" +
-        * Box "VENT STATUS" should change from "VENT PROCEDURE STOPPED" to "WAITING FOR VENT TIMER".  +
-        * Turbo gate valve **I214GV** will be automatically closed and pressure in chamber will start rising (as seen in **I215PG**) {{:wiki:iis800vac_startventing.jpg?500|S800vac Panel Mate: start venting}}.  +
-        * When **I215PG** reads atmospheric pressure, select the box "VENT STATUS" and click "STOP VENTING PROCESS". {{:wiki:iis800vac_stopventing.jpg?500|S800vac Panel Mate: stop venting}}. +
  
-        * The status in the box "VENT STATUS" should change from "WAITING FOR VENT TIMER" to "VENT PROCEDURE STOPPED" +The operational states of the II-GHS are shown in the diagram below.
-        * You can now open the chamber+
  
 +{{:wiki:ii-ppac-ghs-operationalstates.png|}}
  
-===== Pumping Intermediate-image chamber ===== +===== Emptying Detectors ===== 
-Requirements: PanelMate files **S3_Gas_Handling** and **S800Vac** +  - Double check that the detectors have been unbiased. 
-  * Verify that Chamber is closed and pressure-relief valve (north side of the chamber) is properly closed (NOTE: sometimes, due to overpressure from dry N2 during the venting procedure, the O-ring in pressure-relief valve flange is moved out of place) +  - Set “PPAC Setpoint” to 0 Torr. 
-  * Verify that PPACs are not biased by opening the [[HV bias|HV GUI]] +  - Click **EMPTY** on the “GHS_II-PPAC_Main” page to open valves #3 and #4 which will allow for pumping out the gas quickly. 
-  * IMPORTANT: Verify that manual roughing pump valve located near the intermediate-image chamber is closed{{:wiki:manualvalverough.jpg?350|Manual valve rough pump}}+  - When “PPAC Pressure” reads < 0.1 Torr, turn off IG and click **MAN** and then **AUTO**. This will open valve #6 to release the remaining gas into the diagnostics box. 
 +  - Monitor D2340 pumping station and ensure the TMP stays on and TGV remains open. If not, contact the Vacuum Operation group. 
 +  - Valves #1-5 should be closed and valve #6 should remain open. From this state click **VENT** and then **PUMP** to enter pump mode and leave the system in this state until it is ready to be filled. 
 +===== Venting the Chamber =====
  
-  * Insert PPACs/turn on light (Diagnostic Drives PanelMate) and verify condition through sight window on south side of the chamber (be careful no to bump the bullet camera). +From the S800 Main Vacuum page, go to the Intermediate Image RBT_BTS32 D2430 Pumping Station page, and ensure 
-  * Open **S800Vac** and go to page 03 ("Intermediate image box vacuum system sec 15") +  * that the PPACs have been unbiased
-  * Check "PUMPDOWN STATUS INTERMEDIATE IMAGE BOX"; it should read "PUMPDOWN STOPPED". Select that box and click on "START PUMPDOWN". The chamber will not be pumped yet because the manual roughing pump valve is closed. +  * that this pumping station has been isolated by having the gate valves **D2426 BGV** and **D2436 BGV** closed, and that the IG has been turned off, and 
-  * Slowly crack manual roughing valve +  that the turbo pump gate valve **TVG** is closed.
-        * Start slow (< 1 Torr/sec). Chamber pressure is displayed in **I215PG** in **S800Vac** PanelMate. There is also a local display of the mechanical pump pressure on a Granville-Phillips 275 Mini-Convectronwhich is helpful to control rate of pumping. +
-        * Verify PPACs changing shape through sighting window. +
-        * Pump to about 100 Torr before fully opening the roughing valve. +
-  * Once roughing valve is fully open, retract PPACs and turn lights off. +
-  * When the pressure in **I215PG** is below 200 mTorrthe Turbo Pump will start automatically through the following sequence: +
-        * **I214RV** will be closed +
-        * **I214FV** will be opened +
-        * **I214GV** will be opened +
-  * When the pressure ready by **I215PG** is few mTorr, you can turn on the ion gauge **I213IG**. Good vacuum will take ~1-2 hours. +
-  * NOTE: it sometimes happens that the foreline pressure rises above the trip point for the Turbo Pump (e.g. if the pumpdown timer expires before pressure is below 300 mTorr, or there is too much back-up pressure from the chamber when the foreline valve opens). In this situation, you will see that: (1) the turbo pump will stop, (2) the turbo gate valve **I214GV** will be closed, (3) the foreline valve **I214FV** will be closed and the corresponding PanelMate box will turn red and display an error message "Foreline pressure > 2 Torr", and (4) the foreline pressure will be few Torr. In a situation like thisforeline valve needs to be bypassed open (in PanelMate) and the TP needs to be restarted: +
-          Select box labeled "FORELINE VLVE I214FV" and the click on "BYBASS VAC INTERLOCKS OPEN" button +
-          * Select box labeled "TURBO PUMP INTERMEDIATE IMAGE BOX I214TP" and  click "START" +
-          * Turbo pump will start ramping speed. When the TP reaches 40000 RPM, the **I214GV** will open automatically. +
-          * When foreline vacuum gets below 2 Torr, you can select "FORELINE VLVE I214FV" and click "REMOVE BYPASS" +
-          * (Note: sometimes it is necessary to repeat this operation a couple of times) +
-  * At the end of the procedure, close the manual roughing pump valve +
  
 +The TMP can be turned off at this time.
  
 +To vent the chamber:
 +  - Let the Control Room and the Vacuum Operation Group be aware as EXP alarms may occur,
 +  - put the GHS in vent mode by clicking **VENT** (valves #5 and #6 are open),
 +  - monitor **RBT_BTS32:BPG_D2430:VP_RD** and **S800_GHS:PI_D2431:V_RD_AB** in a data browser,
 +  - ensure that **RV**, the valve to the roughing pump, is closed, and
 +  - open **Vent** valve to start venting.
  
 +The PPAC pressure S800_GHS:PI_D2431:V_RD_AB should closely follow the chamber pressure  
 +RBT_BTS32:BPG_D2430:VP_RD up to about 10 Torr, which is the upper limit of the range of the gauge for S800_GHS:PI_D2431:V_RD_AB.
 +===== Evacuating the Chamber =====
  
-===== Filling/Removing gas in Intermediate-image delay PPAC =====+Ensure 
 +  * that the chamber is closed 
 +  * that the pressure-relief mechanism (on the north side of the chamber, see picture below) is sealing (if not, adjust the flange back in place) 
 +{{ :wiki:iipressurereliefmechanism.jpeg?600 |}} 
 +  * that the manual valve (see picture below) is closed. 
 +{{ :wiki:iimanualvalve.jpeg |}}
  
-{{:wiki:ghsiippacs.png?1000|Gas Handling System of S800 Intermediate Image}} +To evacuate the chamber: 
 +  - double-check and make sure that the manual valve is closed, 
 +  - put the GHS in pump mode by clicking **PUMP** (valves #3, #5, #6 are open), 
 +  - close **FV** below the TMP, and 
 +  - open **RV**. 
 +  - A message window, which reads, "Roughing Valve should only be opened if Manual Valve is CLOSED. Confirm Manual Valve is CLOSED before proceeding." of the manual valve is confirmed to be closed, acknowledge the message and click "Yes". This will open **RV**. 
 +  - now open the manual valve slowly while watching the local display of the Pirani gauge. Open slowly such that the pressure reading (in Torr) goes down by about 1 unit per second initially. The valve needs to open more as the pressure goes further down. 
 +  - On the CSS window, after D2430 turns to yellow indicating that the section is in "POOR VACUUM", wait until the BPG reading to go below 100 mTorr before closing RV and opening FV. 
 +  - Turn on TMP, and wait until it reaches the normal rotation (~40,000 rpm). 
 +  - Open **TGV**. 
 +  - Be sure to go back to S3 and close the manual valve. 
 +===== Filling and Running Detectors ===== 
 +  - If in Vent Mode, click **PUMP** then click **RUN** to enter Run Mode. The valves #1 opens and #3 remains open (#5 and #6 will be closed, and the GHS lines will be isolated from the chamber). 
 +  - If in Pump Mode, click **RUN** to enter Run Mode. 
 +  - Plot and monitor IG_D2430:VP_RD while filling. Ion gauge reading will increase but should remain <1E-5 Torr when PPACs are running at full pressure.  
 +  - Step up “PPAC Setpoint” by 1 Torr from 0 to 6 Torr. Allow the “PPAC Pressure” to stabilize for 15 seconds at each step. This should be a quick process but **DO NOT** simply set the “PPAC Setpoint” to 6 Torr as the gas flow could overwhelm the system. 
 +  - PPAC pressure should stabilize after ~1 min. HV may now be turned on to operate the PPACs.
  
-Requirements: PanelMate files **S3_Gas_Handling** and **S800Vac** +===== Troubleshooting ===== 
-  * Verify that PPACs are not biased: +  - If any issues are encountered during fillingrunningor emptyingcontact the Vacuum Operation group for assistance.
-        * Check that the detectors are unbiased by opening the [[HV bias|HV GUI]] +
-        * Notify the system of the bias-off state by selecting the "I214BON_CONFIRM" box in **S3_Gas_Handling** and clicking "PP BIAS OFF CONFIRMED" +
-  * Verify that PPACs are in automatic mode with gas removed (**S3_Gas_Handling**) +
-        * The "GH System Status box should read "Auto Mode Gas Removed" +
-        * If gas is removed but the system is not in the automatic mode, consult the Beam Physicists or Device Physicist. This typically requires to verify that the system is in a controlled status. In particular, the "I214BON_CONFIRM" box should indicate "PP BIAS OFF CONFIRMED", and the only that should be open in **S3_Gas_Handling** are the "Det Bypass" (V5) and "Chmbr Bypass" (V6); the rest of the valves (Gas Sup V1Gas Lin Pmp Out V2Flow Bypass V3Det Return V4, and I214V_NCL (enable) should be closed)  +
-  * Confirm that PanelMate box "I214P_AUTO/MAN Pre Set" reads 5 Torr (the set gas pressure in the detector)  +
-  * Open the gas bottle valve (sitting near the gas handling system) +
-  * PanelMate box "Gas Flow Control" should indicate "OK to Start Gas Flow"Select that box and click on "Start Gas Flow" +
-        * Valve V2 (Gas lin pmp out) will be opened and I214V_NCL will change from closed to "ENABLED" +
-        * Valves V3 (Flow Bypass) and V4 (Det Return) will open +
-        * Valve V1 (Gas supply) will open, and V2, V3, and V6 (Chamber Bypass) will close +
-        * GH System status should indicate "Gas Flowing" +
-        * I214CM Press Rdg will gradually increase to the set value +
-  * When the detector is filled, valve V5 (Det Bypass) will close +
-        * GH System status will indicate "Flow Estab." +
-        * I214BON_CONFIM will change to "PPAC BIAS ASSUMED ON" +
-        * The valves status will be: V1 (open), V2 (closed), V3 (closed), V4 (open), V5 (closed), V6 (closed, I214V_NCL (enabled) +
-        * You can now turn on the detectors+
venting_pumping_intermediate_image_box.1545237746.txt.gz · Last modified: 2018/12/19 11:42 by pereira