venting_pumping_object_box [2018/05/03 09:10]
pereira
venting_pumping_object_box [2023/05/16 12:23]
swartzj
Line 6: Line 6:
   * Open **S800Vac** and go to page 01 ("Production Target Box Vacuum System sec 13")   * Open **S800Vac** and go to page 01 ("Production Target Box Vacuum System sec 13")
   * Verify that OBJ SCI is not biased:   * Verify that OBJ SCI is not biased:
-        * Check that the detectors is unbiased in the HV module sitting in dU6+        * Check that the detectors are unbiased in the HV module sitting in dU6
         * Notify the system of the bias-off state by selecting the "OBJ_SCI_HV CONFIRM" box and clicking "HV CONFIRM OFF"         * Notify the system of the bias-off state by selecting the "OBJ_SCI_HV CONFIRM" box and clicking "HV CONFIRM OFF"
   * Isolate chamber by closing gate valves **I177GV** and **I190GV**   * Isolate chamber by closing gate valves **I177GV** and **I190GV**
   * [[Vacuum control|Turn off]] ion gauge **I188IG**    * [[Vacuum control|Turn off]] ion gauge **I188IG** 
   * Check box "PUMPDOWN STATUS BEAMLINE OBJECT BOX". It should read "Good vacuum"    * Check box "PUMPDOWN STATUS BEAMLINE OBJECT BOX". It should read "Good vacuum" 
 +  * Go to the S800 OBJ station and make sure that the manual valve (see figure below) is closed.
 +
 {{:wiki:objs800vac_pumped.jpg?500|S800vac Panel Mate}}.  {{:wiki:objs800vac_pumped.jpg?500|S800vac Panel Mate}}. 
   * In order to begin venting process, select box "VENT STATUS" and click "BEGIN VENTING PROCEDURE"   * In order to begin venting process, select box "VENT STATUS" and click "BEGIN VENTING PROCEDURE"
         * Box "VENT STATUS" should change from "VENT PROCEDURE STOPPED" to "WAITING FOR VENT TIMER", and then to "VENT VALVE OPEN"         * Box "VENT STATUS" should change from "VENT PROCEDURE STOPPED" to "WAITING FOR VENT TIMER", and then to "VENT VALVE OPEN"
         * Turbo gate valve **I188GV** will be automatically closed         * Turbo gate valve **I188GV** will be automatically closed
-        * Vent valve **I190VV** will be automatically opened. However, the pressure in the chamber (ass seen in **I191PG** will not change because we need to open the manual venting valve+        * Vent valve **I190VV** will be automatically opened. However, the pressure in the chamber (as seen in **I191PG** will not change because we need to open the manual venting valve)
         * Go to the S800 OBJ station and slowly open the manual valve (see figure below). You can see the pressure rising in the Granville-Phillips 275 Mini-Convectron display located on top of the OBJ box.         * Go to the S800 OBJ station and slowly open the manual valve (see figure below). You can see the pressure rising in the Granville-Phillips 275 Mini-Convectron display located on top of the OBJ box.
         * When **I191PG** reads atmospheric pressure select the box "VENT STATUS" and click "STOP VENTING PROCESS"         * When **I191PG** reads atmospheric pressure select the box "VENT STATUS" and click "STOP VENTING PROCESS"