daq:readoutshell [2012/06/07 09:43]
weisshaa created
daq:readoutshell [2014/02/27 16:14] (current)
Line 7: Line 7:
  
 ====== Progress ====== ====== Progress ======
 +(Dirk) On 6/8/12 same thing happened again. Actually geSave send data, most likely the one sent by NSCL DAQ. But GRETINA didn't validate any data. A stop/start fixed the issue, i.e. GRETINA did happily validate....
  
 +(Chris) ~9/3/12 Observations during e11017 indicate that Gretina is failing to validate due to a timestamp syncing issue. ​ Briefly, the timestamps of the digitizers are not reset during run start-up, but S800 receives an "IMP Sync" associated pulse, and the Gretina Trigger system timestamp was reset. ​ This problem may be observed offline by sending a Single IMP Sync; roughly 1 in 30 tries lead to this failure mode.  John Anderson at ANL has been informed and debugging will be attempted during the upcoming software working group meeting on 9/21-22.

QR Code
QR Code daq:readoutshell (generated for current page)