Preparation for tuning

PREPARATION FOR TUNING In S3 vault

Arm dump switches
Make sure object ion gauge is off

Go to page xx on Panel Mate xxx. Check status xxx Ensure viewer is ready

Make sure gas bottles for FP detectors are open
Make sure Intermediate PPACs have gas

In data-U

Start Software tools
PanelMates
NMR GUIs
Barney
Labview Gas Handling System Controls
Labview Bias Controls
Alarm servers and monitors
Linux HV controls (alarm server should be started first)
SpecTcl (alart server should be started first)
Run Control (in coordination with experimenters)
Trigger Control GUI (in coordination with experimenters)
Scalers (in coordination with experimenters)
Put 10 Amps in Spectrograph dipoles
Start gas in detectors

Refer to Section xx (S800 Focal Plane Gas Handling System Operation)

Enable crad04 with a rate limit of 20 kHz (crad04 looks at E1 up)
If it does not interfere with experimenter preparation (see “Unreacted Beam” section below)
Set spectrograph Brho
Start scalers