msu:e14009_to-do_list [2016/09/01 13:10]
brownk created
msu:e14009_to-do_list [2017/01/17 11:35] (current)
brownk
Line 1: Line 1:
 e14009 to-do list: e14009 to-do list:
  
-Before e14002 
   - Test dE PA box   - Test dE PA box
-    * How many working sets (32 channels) do we have? Need 14 minimum +    * How will the biases get from ISEG to PA tower -> 4 cables made by WU (1/9/17)
-    * How will the biases get from ISEG to PA tower+
   - Zero degree detector   - Zero degree detector
-    * Need to design and build (WU and UCONN) +    * Build mount (UCONN)(1/11/17
-    * Modify existing HiRA mount to hold detector (Craig Snow + WU/UConn+    * Build detector/Lead (WU) (1/9/17) 
-  - Find and test dE cables from e10011+    * Modify copper mouth piece (WU)  
 +  - Disassemble HiRA Array (Kyle/Pierre/Sean S 1/4) 
 +    * Install 14 dE detectors (Kyle/Pierre 1/4-1/6) 
 +  - Reassemble Array (Pierre/Sean S 1/6-1/7) 
 +  - Install dE PA box (Sean/Juan 1/6)
   - Test dE's?   - Test dE's?
-    * Is there a good/safe way to test these detectors without having to install them in cans? +    * Add HINP3 to DAQ (Kyle 1/7-1/8) 
-  - May replace 1-2 telescopes with HiRA upgrade +    * Test HINP3 MB with pulsers (Kyle 1/7-1/8) 
-    * Design/modify mounting structure to support these detectors +    * Test bias distribution with new cables (1/9) 
-    * Does Alan have separate calibration beams? +    * Hunt noise  
-    * Test HiRA upgrade CsI (Sean, Pierre)+  - Install mount for zero degree detector (1/11 -1/14) 
 +  - Retest Si E and CsI electronics with pulsers/cosmics (1/16) 
 +  - Alter trigger logic (Trigger will be either EF and EB or EF and EB and Zero Degree)
  
  
-After 14002 +Possible Travel days 
-  - Remove HiRA telescopes and install dE detectors +  * Alan 1/11-1/18, 2/3 
-  - Install mount for zero degree detector +  * Sean/Dan 1/9-1/13
-  - Install dE PA box +
-  - Remount HiRA telescopes and zero degree detector +
-  - Set up dE bias --> ISEG +
-  - Test dE with alpha source +
-   Reduce noise +
-  Retest Si E and CsI electronics with pulsers/cosmics +
-  - Alter trigger logic +
  
 +Other items - added 1/17
 +Implement dE bias for all detectors, test and calibrate dEs
 +Install 0deg detector, internal cabling
 +Setup QDC, test - modify readout and other code to accommodate
 +Install Cu beam blocks - test all
 +Install targets
 +Install beam-pipe section
msu/e14009_to-do_list.1472749834.txt.gz · Last modified: 2016/09/01 13:10 by brownk